Pipe Bursting Equipment: Step-by-Step

Trenchless Pipe Bursting Equipment Manufacturer Representative

Education and Training

RJM Home

Please contact us with questions or prices or support: 800-620-4773

sales@rjmcompany.com

 

Utility Construction

Vacuum Excavation Equipment

 

Pipe Bursting Equipment

 

Pipe bursting steps

 

Electric fusion pipe welder

 

Pipe Repair without Digging

 

Concrete Core Drills

 

 

Pipe Inspection Cameras

 

Drain Cleaning Equipment

Sewer cable machines

Sewer Jetters

Drain Care Products

 

Pipe Locators

RD8000 Cable and Line Locators

RD7000 Underground Cable Locator

RD4000 pipe locators

RD2000 cable locators

CAT & Genny cable locator

GPR - Ground Penetrating Radar

Pipe Sondes

Cable Fault Locators

Metal Detectors

Plastic Pipe Locators

Utility Locator Training

 

Municipal Equipment

Combination Sewer Cleaners

Catch Basin Cleaners

Street Sweeper Equipment

Manhole Cameras 

Odor Control Biofilters

 

 

Site Map

Related links

Link Exchange

Pipe Bursting  - Step-by-Step Operation

Trenchless Technology Education and Training

Step 1: Shore the wall of the hole where the Pipe Genie pipe bursting pulling machine will be situated. Using 4x4 timbers assemble a retaining barrier as shown. Brush out debris from the pipe area. The Pipe Genie will be placed against the barrier.   Pipe bursting equipment shoring

Step 2: Insert 'Push Tube' and then attach the cable.

 

pipe bursting cable chain feeding
Step 3: Pull the cable through Pipe Genie pipe bursting pulling machine and then attach the chain. pipe bursting chain insertion
Step 4: Pull chain through pipe. trenchless technology chain pulling
Step 5: Set frame of pipe bursting pulling machine in the hole. Note Step 1 and ensure frame is butted against retaining barrier as described. Pipe Genie pipe bursting pulling machine
Step 6: Assemble cylinders, pulley and top pulling assembly. trenchless pulling machine head
Step 7: Pass chain around pulley and top box assembly trenchless pipe bursting equipment pulley feed
 

Step 8: Install pipe bursting cones over chain and then install the pipe guide.

pipe bursting heads
Step 9: Hook up pulling chain to block (flat end forward) and hook up retaining chain. pipe genie chain coupling
Step 10: Hook up hydraulic hoses from cylinders to actuator, and from actuator to the supplied power pack. Pipe Genie hydraulic diagram
Step 11: Start the power pack, and start pulling the pipe bursting cones into the old pipe. pipe bursting heads cones

Step 12:Insert chain into new pipe and insert new pipe into the pipe guide.

Step 13:Pull the retaining chain snug and hook up boot. You're ready to begin bursting the old pipe and pulling the new pipe.

pipe bursting chain guide
Step 14: Begin pulling until the pipe is in and the boot is at the bank. Repeat these steps (13, 14, 15) until all the pipe is burst and the new pipe is in. Pipe Genie pipe boot

Step 15 When the pipe bursting heads come through, remove them one at a time by releasing the chain coupler, and then finally release the pipe bursting guide. Once the pipe is fully through, remove the pipe boot and retrieve the chain.

trenchless pipe bursting head removal

Please contact: 

RJM Company

Brian Moss

Office: 360-828-5732, 800-620-4773

Fax: 208-988-6447

sales@rjmcompany.com

9808 NE 134th Av

Vancouver, WA 98682

 

For assistance with pipe bursting equipment